
Phase 4: Warner Avenue to Saint Andrew Place
​Improvements include increasing street capacity from four lanes to six lanes with three through lanes in each direction, 6-foot wide Class IV Protected Bike Lane on each side of the roadway; 6-foot wide parkway, 8-foot wide sidewalk, 14-foot wide raised median, and approximate 8-foot wall where needed. Improvements also include relocating the overhead cables underground, which will be performed by the City’s contractor.

Last Updated: June 27, 2025
Construction

Masonry Wall installation has continued along the West side of Bristol. Sound wall foundation excavation continued, as did formwork for the concrete foundation along the East side of Bristol.

Undergrounding of Utilities

Finalizing outstanding design items with utilities.
Soundwalls

Civil Work

Work scheduled to start mid-2026
Traffic Signals

Work scheduled to start mid-2026
Water Main

Work scheduled to start mid-2026
Storm Drain

Work scheduled to start mid-2026