top of page

Phase 4: Warner Avenue to Saint Andrew Place
​Improvements include increasing street capacity from four lanes to six lanes with three through lanes in each direction, 6-foot wide Class IV Protected Bike Lane on each side of the roadway; 6-foot wide parkway, 8-foot wide sidewalk, 14-foot wide raised median, and approximate 8-foot wall where needed. Improvements also include relocating the overhead cables underground, which will be performed by the City’s contractor.

Last Updated: October 31, 2025
Construction
Work continued setting vaults in order to start the utility undergrounding work on the west side of Bristol.

Undergrounding of Utilities
Finalizing outstanding design items with utilities.
Soundwalls
Civil Work
Work scheduled to start mid-2026
Traffic Signals
Work scheduled to start mid-2026
Water Main
Work scheduled to start mid-2026
Storm Drain
Work scheduled to start mid-2026
bottom of page


